Transformer Sizing Calculator

List the loads a transformer will supply, each with its kW and power factor. The page adds them properly (real and reactive power separately), applies your demand factor and any spare capacity you choose, and gives the minimum kVA. Type the ratings your supplier sells to have the right size picked, and add voltages to see the full-load current on each side.

Transformer
Loads it will supply

Share of the loads running at the same time. 100 means all at once.

Your own planning choice. None is added unless you type it.

Type your supplier's sizes separated by commas, e.g. 63, 100, 160, 250. The smallest one that is big enough is picked.

Formula: S = √(ΣP² + ΣQ²), Q = P × tan(acos PF), I = S ÷ (√3 × V). Full-load currents use the minimum rating

This sizes for steady running load only. Motor starting currents, harmonics from drives and electronics, ambient temperature, altitude and the supply company's rules can all call for a bigger unit. Confirm the final choice with an electrical engineer and the transformer maker.

These are textbook formulas for learning, checking and planning. They do not size cables, fuses, breakers or earthing, and they are not a substitute for a licensed electrician. Any wiring work must follow your local electrical code.

Sizing a transformer from your loads

A transformer is rated in kVA because its windings heat up according to the current they carry, whatever the power factor of the load. The job is to find the kVA of everything that will run at once, decide how much room to leave, and pick a unit at least that large.

Adding loads correctly

Each load has a real power (kW) and a power factor. A motor and a heater of the same kW do not need the same kVA, and their kVA values cannot simply be added, because the reactive parts point in a different direction from the real parts. The page totals kW and kvar separately and combines them with S = √(P² + Q²).

Example: a 60 kW motor group at 0.8 and 25 kW of heating at 1.0 make 85 kW and 45 kvar, so about 96.2 kVA. Adding each load’s kVA on its own would give 100 kVA, slightly too high.

Demand factor and spare capacity

Not everything runs together. If you know from experience or measurements that about 70 % of the connected load runs at the same time, type 70 as the demand factor. Then add any spare capacity you want for future growth. Neither figure has a default beyond 100 % demand and no margin, because they are design decisions, not facts the page can know.

Picking a size

Type the ratings your supplier offers, separated by commas. The smallest one that covers the requirement is chosen, and you see the expected loading as a percentage of it.

Add the primary and secondary voltages to see the full-load current on each side. On three-phase that is kVA × 1,000 ÷ (√3 × voltage).

What else matters

Large motors draw several times their running current while starting, which can dip the voltage on an undersized unit. Drives, UPS systems and LED lighting produce harmonics that add heating. Heat and altitude reduce its capacity. Treat this result as a first estimate for an electrical engineer to confirm.

How to use Transformer Sizing Calculator

  1. Choose single-phase or three-phase and type each load's kW and power factor.
  2. Set the demand factor and, if you want, a spare capacity percentage.
  3. Optionally type the voltages and your supplier's kVA sizes, then read the result.

Privacy: how it works

Calculations run in your browser. The values you enter are not sent anywhere.

Frequently asked questions

How do I size a transformer?

Find the total apparent power (kVA) of the loads running together, add room for growth, and choose the next size up that you can buy. kVA, not kW, matters because the windings carry the full current whatever the power factor.

Why not just add up the kVA of each load?

Loads with different power factors do not add directly. Adding kW and kvar separately and then combining them gives the true total, which is a little less than the simple sum.

How much spare capacity should I allow?

That is a design choice that depends on expected growth, motor starting and the supply company's rules, so nothing is added unless you type it. An electrical engineer should confirm the final size.