Production Capacity Calculator

Enter your working time, number of machines and the cycle time of the slowest step to get the design and effective capacity. Add the demand to get the takt time and see whether you can meet it.

e.g. 1 for a day, 25 for a month.

Time the line does not run: lunch, tea, handover.

Of the slowest step (the bottleneck).

e.g. cavities in a mould.

100 = design capacity. Use your measured OEE for a realistic figure.

Shows takt time and whether you can meet it.

Measure cycle time from a production run

Formulas used

  • available time = days × shifts × (hours per shift × 60 − break minutes)
  • capacity = available time in seconds ÷ cycle time × machines × units per cycle × efficiency %
  • takt time = available time ÷ units needed
  • cycle time = production time ÷ units produced
  • machines needed = ⌈units needed ÷ capacity of one machine⌉

If the takt time is shorter than the time between units your line delivers, the demand cannot be met in the available time. Capacity is rounded down to whole units. Results are rounded for display only; the calculation keeps full precision.

How much can the line make, and is it enough?

Capacity planning compares the time your process needs per unit with the time your customers allow per unit. This page works out both and shows whether they fit.

Available time

Count working days, shifts and hours, and take off the minutes when the line stands still for breaks, lunch and shift handover. Two 8-hour shifts with an hour of breaks each, over 25 days, give 21,000 minutes.

Capacity from cycle time

Cycle time is how long the slowest step in the process takes to complete one cycle. That bottleneck sets the pace of the whole line, however quick the other steps are. Divide the available seconds by the cycle time, multiply by the number of identical machines and by units per cycle (for example the cavities in a mould), and you have design capacity. With two machines at 42 seconds, 21,000 minutes gives 60,000 units.

No line runs at design capacity. Multiply by your efficiency, ideally your measured OEE from the OEE calculator, to get effective capacity. At 85%, the example drops to 51,000 units.

Takt time

Takt time divides the available time by the units customers need. For 40,000 units in 21,000 minutes, takt is 31.5 seconds per unit. The line delivers one unit every 42 ÷ (2 × 0.85) = 24.7 seconds, so it keeps up with room to spare. If demand rose to 60,000, takt would fall below the line’s pace, and the page shows how many machines would be needed at the same cycle time and efficiency.

Measuring cycle time

If you do not know the cycle time, time a steady run. Divide the production minutes by the units made and convert to seconds. A two-hour run that makes 240 units averages 30 seconds each.

Limits

The model assumes one product, a steady cycle time and machines that share the load evenly. Changeovers between products, operator availability and material supply can all cap output below the figure shown.

How to use Production Capacity Calculator

  1. Enter working days, shifts per day, hours per shift and break minutes.
  2. Enter the number of machines, the bottleneck cycle time, units per cycle and your efficiency or OEE.
  3. Add the units needed to get takt time, the load on capacity and the number of machines required.

Privacy: how it works

Calculations run in your browser. The figures you enter are not sent anywhere.

Frequently asked questions

What is takt time?

Takt time = available production time ÷ units the customer needs. With 21,000 minutes available and 40,000 units needed, takt time is 31.5 seconds: the line must finish one unit at least that often.

What is the difference between takt time and cycle time?

Takt time is set by demand. Cycle time is how long your process actually takes per unit. If the time between finished units is longer than the takt time, you cannot keep up.

Which cycle time should I use?

The cycle time of the slowest step, because it limits the whole line. If you do not know it, measure a run: production minutes ÷ units produced, using the helper on this page.