Batch Production Planner

Enter the order quantity, maximum batch size, set-up time and run time per unit, then your working days and hours. The planner works out how many batches you need and when each one starts and finishes on one line.

Largest quantity one batch can hold (tank, oven, lot size).

Optional. Extra units are started to cover it.

Changeover, cleaning, loading.

Up to 24. A window may run past midnight.

Working days

Holidays or shutdown days as YYYY-MM-DD, separated by commas.

Formulas used

  • units to start = ⌈order quantity ÷ (1 − scrap % ÷ 100)⌉
  • batches = ⌈units to start ÷ batch size⌉ (the last batch holds what is left)
  • batch time = set-up minutes + batch quantity × run seconds ÷ 60

Batches run one after another on one line inside the working hours; a batch not finished at closing time carries on at the start of the next working day. Times are wall-clock times on the dates shown; clock changes for daylight saving are ignored.

From an order to a dated batch schedule

Customers ask when an order will be ready. In batch production the answer depends on how many batches the order needs, how long each set-up takes and how the work fits around closing time, weekends and holidays. This planner does the calendar work for one product on one line.

How many units to start

If some output is usually rejected, start more than the order. The planner divides the order by one minus the expected scrap rate and rounds up. For 950 good units with 5% scrap, it starts 1,000.

How many batches

A tank, oven, kiln or lot size limits how much one batch can hold. Divide the units to start by the maximum batch size and round up. With a limit of 400, 1,000 units need three batches: two full ones and a final batch of 200. Each batch pays its own set-up, so a bigger batch size means fewer set-ups and a shorter total time, at the cost of more stock on the shelf.

Batch time

Each batch takes its set-up minutes plus its quantity multiplied by the run time per unit. At 30 minutes of set-up and 36 seconds per unit, a full batch of 400 takes 270 minutes and the last batch of 200 takes 150.

Fitting work into the calendar

Choose the first day, the daily start time, how many hours a day the line works, which weekdays count and any shutdown days. The planner fills each working window in turn. Starting on a Friday at 09:00 with eight-hour days, the first batch ends at 13:30, the second runs until closing and finishes at 10:00 on Monday, and the last is done by 12:30. A window may run past midnight, which suits night shifts.

What it does not do

It plans a single line in sequence. It does not balance several machines, mix products, check material availability or allow for breakdowns. Add a margin for those, and use the production capacity calculator to check the longer-term load.

How to use Batch Production Planner

  1. Enter the order quantity, maximum batch size, expected scrap, set-up minutes and run seconds per unit.
  2. Pick the first working day, the daily start time, hours per day, working weekdays and any days off.
  3. Read the batch count and finish time, check the schedule table and download it as CSV.

Privacy: how it works

Calculations run in your browser. The figures you enter are not sent anywhere.

Frequently asked questions

How is the number of batches worked out?

The quantity to start is the order divided by (1 − scrap %), rounded up. That is divided by the batch size and rounded up again; the last batch holds what is left.

What happens at the end of the working day?

Work stops and carries on at the start time of the next working day, skipping weekends and the days off you list. A batch can therefore start one day and finish the next.

Can it plan several machines or products?

No. It plans one product on one line, batch after batch. For parallel machines, split the order between them and run the planner for each.