Shipping Deadline Calculator
Start from the date your customer or store needs the goods and count back delivery, customs clearance and transit to the latest sailing or flight. Add your booking’s cut-offs to see when cargo must be ready and documents filed.
Planning backwards
Retail launches, project sites and seasonal orders all have a date the goods must be there. The useful question is not when they will arrive but when they must leave, and before that, when the booking, the documents and the cargo itself must be ready. This page starts at the required date and steps back through delivery, customs clearance and transit to the latest departure, then through the cut-offs that come before it.
The cut-offs
A carrier’s booking confirmation lists several deadlines ahead of the sailing. The shipping instruction cut-off is when the details for the bill of lading must be submitted. The VGM cut-off is the last moment to declare the verified gross mass of a packed container. The terminal or CY cut-off is when the loaded box must be through the terminal gate. Exporters add their own: cargo ready at the factory, export clearance done, booking confirmed. Enter each as a number of calendar days before departure and the page puts them in date order.
Example
Goods are needed on Friday 15 January. Delivery takes two working days and clearance three, so the shipment must reach the port by Friday 8 January. With a 20-day transit, the latest departure is Saturday 19 December. A terminal cut-off two days earlier falls on 17 December, and cargo ready seven days before sailing means 12 December. If today is 15 December, that last date has already passed, and the page says so.
Build in slack
These are the latest dates with no margin at all. Vessels are rolled to the next sailing when they are full, flights are offloaded, and inspections take longer than planned. Choosing a departure a week earlier than the latest date is common practice on long routes.
What it does not know
There are no schedules, cut-off rules or transit times inside the tool. Check the result against real sailings, and use the shipment arrival date calculator to see what a particular departure would deliver.
How to use Shipping Deadline Calculator
- Enter the date the goods must arrive and the delivery, clearance and transit days.
- Add the cut-offs from your booking as days before departure, or remove the ones you do not need.
- Read the latest departure and every deadline in order, and save them to your calendar.
Privacy: how it works
Calculations and the calendar file are made in your browser. Nothing you enter is sent anywhere.
Frequently asked questions
What are VGM and CY cut-offs?
The VGM cut-off is the last time to submit the container’s verified gross mass to the carrier. The CY (terminal) cut-off is the last time the full container can be delivered to the terminal for the sailing.
Why are cut-offs counted in calendar days?
Carriers state them as dates before the vessel departs, whatever the weekday. Enter how many days before departure each one falls on your booking.
What if a date is already past?
The page warns you. The deadline cannot be met with those durations: try a faster mode, a shorter route or agree a later date.