Reorder Point Calculator
The reorder point is the stock level at which you place the next order so it arrives before you run out. Enter average demand, lead time and safety stock; add your stock figures to see whether it is time to order.
From placing the order to having the stock ready to use.
Work it out with the safety stock calculator; blank = none.
A trigger, not a target
The reorder point is the stock level that tells you to place the next order. Set it right and the delivery lands as stock reaches its buffer. Set it too low and you run out while waiting; too high and the shelves fill up with stock you did not need yet.
How it is built
Reorder point = average daily demand × lead time in days + safety stock. The first part is what you expect to sell or use while the order is on its way. The second part is the cushion for days when demand jumps or the delivery is late. If you type weekly demand, the page divides by 7; monthly demand is divided by 365 ÷ 12, and yearly by 365.
Example
A workshop uses 40 filters a day. The supplier takes 7 days from order to delivery, and the workshop keeps 100 as safety stock. Expected use during the wait is 280, so the reorder point is 380.
With 500 on the shelf and nothing on order, the stock position is 500. At 40 a day it falls to 380 in 3 days, which is when the page says to order. Now suppose the shelf holds 300, another 100 are already on order and 20 are promised to customers. The position is 300 + 100 − 20 = 380, exactly at the trigger, so the answer is to order now.
Use the position, not the shelf count
Comparing the shelf alone with the reorder point leads to double orders: stock already on the way is forgotten and ordered again. Backorders are subtracted because those units are already spoken for.
Getting the inputs right
Lead time should run from the moment you decide to order to the moment the goods can be used, including approval and receiving. The lead time calculator can add up those stages or measure them from past orders. For the buffer, the safety stock calculator turns demand variation and a chosen service level into a number of units.
How to use Reorder Point Calculator
- Enter average demand and choose day, week, month or year.
- Enter the lead time in days and, if you keep one, the safety stock.
- Optionally enter stock on hand, on order and owed to customers to see whether to order now.
Privacy: how it works
Calculations run in your browser. The figures you enter are not sent anywhere.
Frequently asked questions
What is the reorder point formula?
Reorder point = average daily demand × lead time in days + safety stock. For example 40 units a day, 7 days lead time and 100 units of safety stock gives 380.
Should I compare it with the stock on the shelf?
Compare it with the stock position: on hand plus already on order, minus backorders. Otherwise stock you have already ordered is ordered again.
How do I choose the safety stock?
Use the safety stock calculator, which works it out from how much demand and lead time vary and the service level you choose.