Aggregate Quantity Calculator

Find how much coarse aggregate to buy for a concrete job. Enter the volume or the slab sizes and the mix ratio to get m³, cubic feet, brass and an approximate weight, with the cement and sand shown alongside.

How will you give the quantity?
Mix and assumptions (all editable)

These volume ratios are customary site practice, not figures from IS 456:2000. Typical, change to your engineer's figure.

Ratio by loose volume (cement : sand : aggregate). Typical, change to your engineer's figure.

Wet concrete shrinks as voids fill; 1.52 to 1.57 is common. Typical, change to your engineer's figure.

Added on top of every material. Use 0 to see the net quantity.

Loose cement, used to turn volume into kg. Typical, change to your engineer's figure.

50 kg is the usual bag in India.

Only for the tonnes figure; damp sand differs. Typical, change to your engineer's figure.

Only for the tonnes figure. Typical, change to your engineer's figure.

IS 456 check for M20: Table 9 sets the nominal mix by mass: per 50 kg bag of cement, at most 250 kg of total dry aggregate (fine to coarse generally 1:2 by mass, between 1:1.5 and 1:2.5) and at most 30 litres of water.

IS 456 allows nominal mixes only up to M20, prefers design mixes, and says ingredients should be batched by mass; volume batching only where weighing is not practical. Source: IS 456:2000, clause 9.3 and Table 9 (checked 2026-11-19); Source: IS 456:2000, clauses 9.1, 10.2.3 and 10.2.4 (checked 2026-11-19).

This is an estimate of material quantities, not structural design. Concrete grade, mix proportions, cover, bar sizes and spacing must come from a qualified engineer and your drawings.

Coarse aggregate for concrete

Coarse aggregate, also called gravel, crushed stone, metal, gitti or jelly depending on the region, makes up the largest share of a concrete mix. Running out halfway through a pour is expensive.

How the page works it out

Enter the concrete volume directly, or its length, width and depth. The page multiplies the volume by the dry volume factor (1.54 unless you change it) and then takes the aggregate share of the mix ratio. In 1 : 2 : 4 concrete, aggregate is four parts of seven.

Worked example

A driveway slab of 10 m × 3 m at 100 mm thick holds 3 m³ of concrete. In a 1 : 2 : 4 mix: 3 × 1.54 × 4 ÷ 7 = 2.64 m³ of aggregate. That is about 93.2 cft, or 0.93 brass, and roughly 3.96 tonnes at a loose density of 1,500 kg/m³. The same slab needs about 19 bags of cement and 1.32 m³ of sand, shown on the line below the result.

Choosing the stone

The size and grading of the aggregate matter as much as the quantity. Most slabs, beams and columns use 20 mm graded stone; thin sections and closely spaced bars may need 10 or 12 mm. IS 456:2000 Table 9 notes that the fine to coarse proportion of a nominal mix should shift with aggregate size and sand grading (1:1.5, 1:2 and 1:2.5 by mass for 10, 20 and 40 mm with Zone II sand). Your engineer’s mix takes priority over any preset here.

Weight versus volume

Quarries often sell by weight. Loose crushed stone typically weighs somewhere around 1,400 to 1,600 kg per cubic metre depending on its shape and grading, which is why the density field is editable. Ask for the figure your supplier uses and type it in.

What this page does not do

It does not design a mix or check strength. It estimates quantities only. For the whole concrete take-off with several members, use the concrete volume calculator.

How to use Aggregate Quantity Calculator

  1. Enter the concrete volume, or the length, width and depth.
  2. Pick a mix ratio preset or type your own, and check the assumptions.
  3. Read the aggregate in m³, cft, brass and tonnes.

Privacy: how it works

Calculations run in your browser. The sizes you enter are not sent anywhere.

Frequently asked questions

How much aggregate is in 1 m³ of concrete?

With 1 : 1.5 : 3 and a 1.54 dry volume factor, about 0.84 m³ (29.7 cft). With 1 : 2 : 4 it is about 0.88 m³.

Which aggregate size should I use?

20 mm is common for slabs, beams and columns, but the right size depends on the member and the bar spacing. IS 456 Table 9 also links the fine to coarse proportion to aggregate size, so follow your engineer.

Can I order by weight instead of volume?

Yes. Type the bulk density your quarry or supplier uses; the page uses 1,500 kg/m³ as a typical loose figure for crushed stone.